2025 Construction Underway as Weather Warms

Spring Construction 2025

Early March 2025 | On-site stump removal

As spring warms our area, anticipation builds for upcoming construction plans. Being just over a year since Oliver Paipoonge Township approved the project, the progress towards Pennock Village has been moving steadily along. There were conditions to satisfy with that approval – a normal part of the process – before final building permits could be issued. Current status on conditions include:

• Approved sewage treatment design with the Thunder Bay District Health Unit

• Finalized site plan and drainage drawings with the Engineer & Architect, outlining all details of proposed site completion

• Authorized issued permit by Lakehead Regional Conservation Authority, which allows for the construction and crossing of the tributary in the regulated area

• Currently finalizing the legal descriptions and lot layout, surveyed/registered with the Ontario Land Registry Office

• Currently finalizing the declaration of how the development will be managed, showing rights of access

• Registered Notification Agreements to inform prospective Residents of the nearby racetrack & industrial property

Additional required site preparation studies already completed include:

• A Hydrogeological Groundwater Capacity study

• A Hydrogeological Sewage study

• A Traffic Study Brief for the Ministry of Transportation and

• A Stormwater Management study

We are in the final stages of completing these items to receive council-approved sign off on their Planning Report. With that, we anticipate a timely start to the beginning of the 2025 construction season including the start of the proposed Phase One development Garden Homes.